Using innovative rail industry technology to transform station operations.
JFRail developed the Stations Resourcing Initiative (SRI) and has and implemented it across several Network Rail-managed stations over the past three years. The initiative uses innovative rail industry technology to transform station operations from a static, location-based model into a task-led, optimised approach supported by workforce planning tools and efficient rostering. This means station staff are deployed based on tasks and demand, rather than fixed locations. JFRail successfully delivered this approach in partnership with software company SISCOG, using Train Operator resourcing technology.
Network Rail (High-Speed) first engaged SRI to improve productivity at stations. The initiative delivered significant productivity improvements whilst also enhancing employee engagement through initiatives such as team days, collaborative working, structured breaks and administration time for managers. Due to the diversity of benefits, SRI has attracted further interest at other Managed Stations; SRI has been tested and deployed at Euston Station, with a pilot proposal outlined for Birmingham New Street. Feasibility studies demonstrate a 10% reduction on average in Full-Time Equivalent (FTE) headcount at these stations.
Manchester Piccadilly Station presented a unique set of challenges, creating an opportunity to undertake an additional SRI feasibility study. The Stations Management team faced increasing customer assistance demand, employee engagement challenges, CP7 efficiency targets and the need to align station resources with the wider GBR initiative. Following a joint site visit, the JFRail team identified several operational inefficiencies at the station, including fragmented station operations that required split resourcing, growing customer assistance demands without data-led resource planning and limited use of availability and utilisation data to inform staffing decisions.
The study assessed how to optimise task-based activity for key station roles through structured work diagrams, workforce planning (based on availability and utilisation data) and rosters. To achieve this, JFRail followed a structured methodology. This included:
This approach delivered a series of valuable outputs to inform key recommendations for optimisation:

As part of the baseline process, JFRail also developed a comprehensive workforce calculator using availability and utilisation data. This included a raw data calculator (considers actual release time from the roster for all roles), a normalised calculator (considers industry-expected levels of release and coverage required for all roles) and an overview report, detailing the differences between the raw data and normalised calculators. This helps Station Management teams to optimise station resourcing by reducing the impact of current release and resource coverage requirements. Using the assessment outputs, JFRail worked with the Client to identify additional opportunities for further efficiencies. This included, for example, merging activities, removing roles and combining rosters.
JFRail’s approach generated a series of findings which informed a Station Resourcing Action Plan and further enhancement options. Using a workshop-based approach with the Station Management team, JFRail selected four options from the outputs for further development and validation. The team developed new diagrams, base rosters and workforce calculators for each option, comparing outcomes to identify which options yielded the greatest efficiencies.
The SRI process at Manchester Piccadilly highlighted:
Based on the results, JFRail presented five key recommendations to optimise station resourcing at Manchester Piccadilly, considering various pathways for the implementation of options and elements of the Manchester Piccadilly Station Resourcing Action Plan.